How to build a commodity coverage plan from your demand forecast

A coverage plan says how much of your forecast is already bought, how much is still open, and when the open part must be booked.

Start from the forecast

List each commodity line with its volume, unit and the month coverage must start.

  • One row per commodity and grade
  • Use the same unit as your supplier contracts
  • Note the budget price finance has approved

Subtract what is already covered

Coverage needed = forecast minus current position. This open volume is your exposure.

Set a book-by date

Work back from the coverage start date, allowing time for quotes, approval and contracts.

  • Request quotes 4–6 weeks ahead
  • Allow one council cycle for approval